Thursday, 5 July 2018

Custom-Built Albi Home - Green Tape!



Nancy Enjoying all the Space
Custom-Built Albi Home - Green Tape!

Orientation Day – Green Tape Day!

Albi Riverstone organizes an Orientation Day for us, a week before the date to move in. It's a day filled with green tape. We move through the house with careful eyes trying to spot as many imperfections as we can, then stick a piece of tape on them. It becomes a game - who can find the most! These may be small splotches of grout or drips that are not cleaned perfectly. Our site super calls them 'goobers'. We also check the ceilings, corners and the floors for marks or damage. By the end of the day our house looks like a polka-dot mix of green and white! We also learn about our appliances, the thermostats and any regular maintenance that we are going to need to do etc... but the main purpose of the HOO is to use up as many rolls of green tape as possible. 

Our Driveway – Oops - What?

Driveways are very often not ready for possession and ours was no different. We actually had the driveway poured about a week before we moved in so we were expecting to be able to walk on it but not drive on it. You need to wait 28 days before you can drive on it. The Monday before possession we get a call from the builder saying, "Sorry, but we need to tear it out – We're not happy with the finish!" So we got lucky because now they explain that we can go ahead and drive on it. The moving truck is going to be able to pull right up to the door!

Proud Owner 
Move-In Day

We are crazy excited and can barely sleep the night before. Move-In Morning is full of anticipation with all the build-up that has been leading to it! But it is also stressful - the movers are coming at noon to our old house and possession of the new house starts at 10am. We are still frantically packing up the last little bits! During the first walk-through of possession we check to make sure all our green tape is gone. There is a painter on-site so that if we see any more imperfections they can fix them right away. Awesome!

Oops Again - Forgot to Pack a Lunch

We totally forgot about lunch. But the construction crew has actually brought in a huge platter of sandwiches, cheese and drinks for all of us! So thoughtful! Nancy and I go through the house, excited and also anxious. The lawyers still haven’t called to tell us the money has been received by our mortgage company! The stress is unbelievable but soon all the paper work is done. The lawyers did a great job.

Movers – Wow -These Guys are Great!

As our possession meeting wraps up we see the time and rush back to our old house to meet the movers. We start to panic. It's raining! The professional crew work hard. Four guys with a big truck make the furniture (wrapped-up) and boxes go in quickly. They cover our new floors with runners to protect the carpet. It takes three trips and seven hours of packing, unpacking, putting the boxes and furniture in the right rooms.

We are finally in. The house is ours but the fun isn’t over yet. There is still so much to do with all the things that we have planned on, after we take possession but more on that in the next blog!

Friday, 22 June 2018

Albi - Custom-built Home - Floors Can Be Beautiful


Floors Can Be Beautiful.



Now that the protective covers are off we can admire our floors. They are gorgeous! Nancy and I are getting very excited to move into our brand new custom-built Albi home. No more delays.



Move-in Date – Soon!

We make arrangements with a Moving Contractor to come when we are ready to move the big stuff. They give us a quote of $1,200, for a two-story, four-bedroom house with a finished basement. I think the price is right. The small packing we start to do ourselves.

Packing Party with Friends

How did we accumulate so much? Now, we start to feel the pressure. But, we have a great idea. Let's have a 'packing party' and get our friends to lend a hand. We invite a few close friends. They are happy to help.  We order in food. The night is fun for us and it's nice to know everyone is carried away with the excitement too. We have about 20 boxes to go in one night. There is still a lot more packing to do. We make several trips to get more boxes from Home Depot.

Fencing between Good Neighbours

There are still some extra costs that we need to deal with. For example, we knew about our requirement to help pay for the fencing on one side on the neighbouring property. When we actually move in, it moves to the top of the priority list. But planning a house-warming party is also on the agenda. Since we have out-of-town relatives who will visit this summer, we may actually have two!

Friday, 15 June 2018

Albi Custom-built Home - Drywall – Whoo-hoo!


Drywall – Whoo-hoo!


Before the drywall was up, light was just coming in everywhere because there were no walls!! Now we can see exactly what the natural light looks like and it's absolutely wonderful and bright! So many windows it's going to be expensive to cover!! Once the drywall is finished we can also start to take measurements and start shopping for furniture, for example the dining room table.

Kitchen Cabinets -Wow!

Looks can be deceiving. The camera angle makes the kitchen look bigger. It's smaller than what you may imagine but there's room for everyone. The counter tops are just what we ordered. It is a dream. We love it.

Lights - Tiles - Backsplash - Fireplace - The Works!

Nancy and I are happy about our choices, especially with the tile on the floors and walls of the master bathroom. We love the backsplash in the kitchen too. Also, the lighting system we decided on is turning out nicely through-out the whole house. Our lights are modern, like us.

Can't Wait to See the Flooring

The floors once laid, were covered up immediately to protect them. We can't wait to see them. We know we have to be patient.

Thursday, 7 June 2018

HVAC Last Chance – Before the Inspector Comes


HVAC Last Chance – Before the Inspector Comes
The Heating, Ventilation and Air Conditioning (HVAC) system is a sub-
discipline of mechanical engineering, based on the principles of thermodynamics, fluid mechanics and heat transfer. Basically it's the comfort, health and safety of the air in your house. It is an important part of your home. But for our custom-built Albi home, it is more complicated due to the legal suite.
Challenges with a Legal Suite
Building a legal suite from the get-go has saved a lot of time and effort vs. doing it afterwards, but there certainly are some negatives to the process. Primarily the ductwork in the furnace room has to be routed a certain way because it all has to be dry-walled prior to the installation of the furnaces. This basically results in the ducts all being lowered and a very complex system being designed to keep both living spaces completely separate for ventilation etc...

The Duct Work - A Wonderful Mess!
The duct work seems like the challenge similar to a difficult maze. Mike from Arpi’s did a great job.  He is an Absolute Pro when it comes to designing a system that maximises my ceiling height throughout the basement while giving us the ideal flow of air and heat. He designed a system that is exactly what and where we needed it! I am very impressed with his skills! In the end the ductwork looks like it was a puzzle put together with perfect accuracy.

Plumbing, Electrical and Mechanical – Smooth Sailing
Now here is where things get really intense and exciting for me. I don’t know why but I have always been fascinated with what is going on behind the walls in my house. Here is my chance to not only see everything but see how it all goes together and makes my house tick! Progress is fairly quick in most areas. The plumbing goes in fairly smoothly, mechanical and the electrical too. Insulation is installed. We are happy and excited that the city inspectors can now come through. It is the last chance, forever, because the drywall is next. But the Move-in date is ---no! Delayed.


Friday, 20 April 2018

Custom-built Home - Extras, Extras!


Nancy is Excited
Custom-built Home - Extras, Extras!

Some options in a custom-built home can cost a lot more than expected! Some quotes from the builder prompted us to do some research. We decided to do some installations after and we removed them from the builder's plans, for example, closet organizers, window coverings, and the backyard deck. But a word of caution!

A Word of Caution! After Possession Expenses

Initially we felt that after the house was built we could do some things cheaper ourselves like the heater in the garage, air conditioning, water softener, and irrigation system and this is proving to be true. Our decisions were based on future cost savings especially since keeping in mind, they would be much more costly if we had to rip out walls and renovate afterwards. With these items properly roughed in, we knew that we could install them some time in the future when we had the extra money. A little planning and foresight here into what we knew we would eventually want in our dream home has enabled us to save thousands.

Siding! The house starts to look real!

There is something new to see every day at the job site. Watching the siding go on gives the house an almost-finished look. Mistakes are made but when things happen I make a call and soon everything is sorted out. I have respect for all trades people, with me on site every day. I try hard not to get in their way but they appreciate me there to point out some of the changes I made to the stock floorplans helping them avoid extra work. They work hard and typically are not on salary so being able to finish quickly and efficiently is the best for them! It is really exciting to see the progress being made.

The Bonus Room - Nancy is Excited

My parents built an open-concept house with a cathedral ceiling. Growing up, I remember I enjoyed the space and think it's a good idea for our new home. Nancy thinks it's a good idea too, so we designed the living room to be open from above. We also chose the corner lot to give us the option for a ton of windows, some people might say too many!! The window coverings cost a small fortune!




Friday, 2 March 2018

Custom-built Home - Stay on Top of It!


Custom-built Home - Stay on Top of It!

Last House with Albi Estates

Cody, our framer, will soon be moving out-of-province so this will be his last house with Albi Estates. He is awesome and he is highly professional at what he does. We were lucky to have him. We wish him well wherever he goes next.

Keeping on Top of Things

We have made many decisions so far. We sign off on tile, carpet, shelving and mirrors. I drop by the house to make an inspection. I see that they have the plumbing installed. When Nancy and I were making plans, we asked and paid thousands of dollars for high-quality fixtures such as a special shower head in the master bathroom. When I saw the installation, I realized that to my dismay only the rain can was installed.

Missing Shower Head – Huh?

Looking at the shower stall, I realize that we are missing the shower head. How does this happen? It could be that we made that decision over a year ago and it was lost in the translation from: Albi-initial-plans-to-builder-to-plumber. Things like that can happen over that lengthy a time-line. Also missing is a water line to the freezer, no drain in the bathroom downstairs and the fridge is in the wrong place.

I Visit the Construction Site Every Day

After a telephone call all the issues are quickly fixed. Things are progressing at a nice pace. Nancy and I continue to talk about decorating ideas. It is fun!

Friday, 16 February 2018

We Have a Wall – Yes!


We Have a Wall – Yes!

Our Albi Home - The House Takes Shape

The kids never get tired of visiting the construction site. We drive up to and go around the house building every day after school. Nick loves the action, especially with all the trucks and machinery and workers and assembling going on. When the foundation wall-structure is in, they deliver a prefab front entrance, porch and steps. Then they start work on the sub-floor. It takes weeks, more or less and then we actually can walk up and in to what will be our house. Next, a wall...

We Have a Wall – Yes!

We stop by the lot and see a wall going up. The kids' eyes are glued to the moving crane and chatty with excitement. Cody, the framer, operates the crane like a pro. As we watch, Nancy and I take pictures. Out of the corner of my eye I see that like me, she is grinning from ear to ear. Soon four walls are up. We leave but miss the house so later ...we drop by with a Subway sandwich for hard-working Cody.

Roof, Upper Floors, Windows then More Stairs

When the upper floor is done, the stairs go in. We get to finally go upstairs and then get a better feel for the house. We designed this house. We are proud and thrilled. The windows are installed. Things are getting really exciting. We get to see what the view will be like. The scene is interesting from up that high. We do see houses of course, but all around we get to see a bit of the escarpment. Nice.

More Framing – Interior Walls

With the interior walls framed in, we get a good sense for how big the rooms will be although we know if will feel different once the drywall is up. Our imaginations run wild with decorating ideas. In the plans our tall walls are over-engineered so could have pure glass and wood with a bulk head so we can hang curtains and install lights. The framer used actual floor joists for the bulkhead so it will reinforce the structure of the wall even more and I can walk on it? We love that decision. We have a lot to talk about. Meah walks into what will be her room. Later she calls, her grandmother, her Baba and says that she loves her room. What eight-year old wouldn't?